Start with 100 sprockets.
Shop B quotes less for the parts. Both offers cover drawing SP-17, revision C.
| Quoted cost | Shop A | Shop B |
|---|---|---|
| Unit price | €18.00 | €15.75 |
| 100 pieces | €1,800 | €1,575 |
Fixed-fee engineering review
Before you award a machined part, find out what the lower price leaves open. I compare two supplier offers against one drawing revision and one batch quantity.
| Quoted scope | Offer A | Offer B |
|---|---|---|
| Price per piece | €18.00 | €15.75 |
| Hardening | 56–60 HRC | Unspecified |
| Export crate | Included | Excluded |
| Fixture | €160 | €280 |
The €225 difference in piece prices falls to €105 for the first lot once fixtures are included. Treatment, packing and transport are still open.
Illustrative quote review
Two machine shops quote the same sprocket. Follow the first lot from piece price to the questions still open.
Shop B quotes less for the parts. Both offers cover drawing SP-17, revision C.
| Quoted cost | Shop A | Shop B |
|---|---|---|
| Unit price | €18.00 | €15.75 |
| 100 pieces | €1,800 | €1,575 |
Shop B’s fixture costs €120 more. Its first-lot advantage drops from €225 to €105.
| Quoted cost | Shop A | Shop B |
|---|---|---|
| 100 pieces | €1,800 | €1,575 |
| Fixture | €160 | €280 |
| First-lot subtotal | €1,960 | €1,855 |
The €105 is provisional. Before award, ask Shop B to price or confirm each item and compare delivery to the same destination.
Illustrative walkthrough · Silent · 0:35
Follow two offers for 100 sprockets. A fixture charge changes the comparison before either part has left the factory.
Request a proposal for my partFor 100 pieces, A quotes €1,800 and B €1,575. Add €160 for A’s fixture and €280 for B’s. First-lot subtotals become €1,960 and €1,855. The remaining gap is €105. Ask B to confirm heat treatment, testing and crating in writing. Then compare the full cost to the same destination.
Fees & deliverables
An editable Excel file with example figures. Replace them with your supplier prices, one-time charges and delivery assumptions.
Download ExcelI complete the comparison for your part and write a recommendation you can circulate. You approve the fee and delivery date before work starts. Calls, visits and extra revisions are priced separately if needed.
Request the fixed feeWhat purchasing can commission
Send the part family, quantity, destination and award date. A short description is enough for the free fit check. We agree how to exchange drawings and offers before you share them.
For a desk review I quote one fixed fee for two existing offers, one drawing revision and one lot. If the documents leave a material question open, the note identifies it. Supplier follow-up, extra revisions, site visits and testing can be scoped separately before you approve any additional fee.
You get a side-by-side worksheet and a written recommendation. Each material gap has a question, the person who can answer it and the evidence needed before award.
For the receiving plant
For a delivery to Italy, the US or Canada, name the receiving site, currency, trade term and delivery point. I identify what each factory has included. Your forwarder supplies the transport quote and your importer or broker confirms the local charges.
Keep one-time fixture costs separate from repeat-order prices. If the drawing is in inches and a supplier responds in millimetres, record the original tolerance and ask engineering to approve the inspection basis.